This is historical material, "frozen in time." The web site is no longer updated and links to external web sites and some internal pages will not work.

HDOT News Release: Weekend lane closures

Posted on May 30, 2019 in Latest Department News

OAHU LANE CLOSURES

FOR THE WEEKEND OF MAY 31 – JUNE 2

 

PLEASE NOTE:

Lane closure schedules may change at any time without further notice.
All projects are weather permitting.

 

— H-1 FREEWAY —

 

1) HONOLULU (24-HOUR WORK)

24-hour shoulder closure on the H-1 Freeway in the westbound direction between the Pali Highway overpass and the Middle Street underpass on Friday, May 31, through Friday, June 7, for guardrail and shoulder improvements.

 

2) HONOLULU (24-HOUR WORK)

24-hour shoulder closure on the H-1 Freeway in the eastbound direction in the vicinity of the Liliha Street overpass on Friday, May 31, through Friday, June 7, for guardrail and shoulder improvements.

 

3) HONOLULU (WEEKEND/NIGHT WORK)
Two right lanes closed on the H-1 Freeway in the westbound direction between the Queen Emma Street overpass and the Palama Street offramp (Exit 20C) on Sunday night, June 2, through Friday morning, June 7, from 9 p.m. to 4 a.m., for guardrail and shoulder improvements. The School Street onramp to the H-1 Freeway westbound will be closed during this time. Motorists will be detoured via Palama Street and Vineyard Boulevard.

 

4) PEARL CITY (WEEKEND/NIGHT WORK)

Two right lane closures on the H-1 Freeway in the eastbound direction between the H-1/H-2 merge and the Aiea Heights Drive overpass on Friday night, May 31, through Saturday morning, June 1, from 6:30 p.m. to 6:30 a.m. A third lane will be closed from 7:30 p.m. to 6 a.m., for precast panel work. The shoulder lane will be closed.

 

For more information, please visit the project website at https://h1waimalu.com/

 

5) PEARL CITY TO AIEA (WEEKEND/NIGHT WORK)

Two left lane closures on the H-1 Freeway in the westbound direction between the Kaamilo Street overpass and the H-1/H-2 Split on Friday night, May 31, through Saturday morning, June 1, from 8 p.m. to 10:30 a.m., for precast panel work. A third lane will be closed from 9 p.m. to 9 a.m. A fourth lane will be closed from 11 p.m. to 9 a.m. The shoulder lane will be open.

 

For more information, please visit the project website at https://h1waimalu.com/

 

6) PEARL CITY TO AIEA (WEEKEND/NIGHT WORK)

Up to four lanes will be closed on the H-1 Freeway in the eastbound direction between the H-1/H-2 merge and the Aiea Heights Drive overpass on Saturday night, June 1, through Sunday morning, June 2, for pre-cast panel work. Two lanes will be closed on Saturday night from 7 p.m. to 9 a.m. A third lane will be closed from 8 p.m. to 7:30 a.m. A fourth lane will be closed from 11 p.m. to 7:30 a.m. The shoulder will be open.

 

For more information, please visit the project website at https://h1waimalu.com/

 

 

— FARRINGTON HIGHWAY (ROUTES 93/930) —

 

1) KAPOLEI (WEEKEND/NIGHT WORK)
Left lane closure on Farrington Highway in the westbound direction between the Farrington Highway onramp and Waiomea Street on Sunday night, June 2, through Friday morning, June 7, from 10 p.m. to 5 a.m., for overhead sign installations.

For more information, visit the Kapolei Interchange Complex Phase 2 project website at https://www.buildkapolei.com/

 

2) MAKAHA (WEEKEND/NIGHT WORK)

Lane closures on Farrington Highway (Route 93) in the westbound direction between Leihoku Street and Ala Hema Street on Sunday night, June 2, through Friday morning, June 7, from 9 p.m. to 4 a.m., for repaving work as part of the Farrington Hwy Resurfacing, Phase II from Hakimo Road to Kili Drive project. Traffic will be contraflowed.

 

3) MAKAHA (WEEKEND/NIGHT WORK)

Lane closures on Farrington Highway (Route 93) in both directions between Ala Hema Street and Makaha Valley Road on Sunday night, June 2, through Friday morning, June 7, from 9 p.m. to 4 a.m., for installation of loop detectors as part of the Farrington Hwy Resurfacing, Phase II from Hakimo Road to Kili Drive project. Traffic will be contraflowed.

 

  • Sunday through Tuesesday: Lane closures in the eastbound direction.
  • Wednesday through Friday: Lane closures in the westbound direction.

 

4) MAKAHA (WEEKEND/NIGHT WORK)

Roving lane closure on Farrington Highway (Route 93) in the westbound direction between Makaha Valley Road and Kili Drive on Sunday night, June 2, through Friday morning, June 7, from 9 p.m. to 3:30 a.m., for striping work as part of the Farrington Hwy Resurfacing, Phase II from Hakimo Road to Kili Drive project.

 

 

— KALANIANAOLE HIGHWAY (ROUTES 61/72) —

 

1) WAIMANALO (WEEKEND/NIGHT WORK)

Access to Mekia Street will be closed from Kalanianaole Highway (Route 72) in both directions beginning at 7 p.m. on Sunday night, June 2, continuously through 3 p.m. on Friday, June 7, 24 hours a day, for roadway reconstruction and utility work. Mekia Street will be accessible by Poalima Street and Lukanela Street.

 

For more information, please visit the Kalanianaole Highway Improvements project website at https://www.gloverltd.com/projects/kalanianaole_highway/.

 

 

— KAMEHAMEHA HIGHWAY (ROUTES 80/83/99) —

 

1) WAHIAWA (WEEKEND/NIGHT WORK)

Alternating lane closure on Kamehameha Highway in both directions between Kilani Avenue and Wilikina Drive on Friday night, May 31, from 9:30 p.m. to 4 a.m., for sign and marking work.

 

 

— PALI HIGHWAY (ROUTE 61) —

 

1) NUUANU TO KANEOHE (WEEKEND AND WEEKLY CLOSURE)
Closure of the Pali Highway (Route 61) in both directions between Waokanaka Street and Kamehameha Highway on Saturday, June 1, through Friday, June 7, over a 24-hour period, for slope stabilization work following the landslide. The Kailua-bound lanes will be temporarily open during the schedule below.

 

From Monday, June 3, through Friday, June 7:

  • Honolulu-bound traffic will be contraflowed in the Kailua-bound lanes between Saint Stephen’s Diocesan Center and Nuuanu Pali Drive from 5 a.m. and 9 a.m.
  • The Kailua-bound direction will be open from 3 p.m. to 7 p.m.

 

2) HONOLULU (WEEKEND/NIGHT WORK)

Left turn lanes closed on the Pali Highway offramp (Exit 21A) from the eastbound H-1 Freeway on Sunday night, June 2, through Friday morning, June 7, from 8 p.m. to 5 a.m., for the Pali Highway Resurfacing project. Traffic will be detoured to turn right at Pali Highway then make a u-turn at the Vineyard Boulevard intersection.

 

3) HONOLULU (WEEKEND/NIGHT WORK)

Closure of the Pali Highway onramp to the eastbound H-1 Freeway on Sunday, June 2, through Friday morning, June 7, from 6:30 p.m. to 2:30 a.m., for the Pali Highway Resurfacing project. Traffic will be detoured to Vineyard Boulevard where drivers may access the H-1 Freeway eastbound onramp.

 

4) NUUANU (WEEKEND/NIGHT WORK)

Closure of the Pali Highway (Route 61) in the Honolulu-bound direction between the Wylie Street overpass and Pauoa Road offramp on Sunday night, June 2, through Friday morning, June 7, from 6:30 p.m. to 2:30 a.m., for the Pali Highway Resurfacing project. One lane will be tentatively closed from 2:30 a.m. to 5 a.m. Detour signs to Wylie Street and Nuuanu Avenue will be posted.

 

For more information, please visit the Pali Highway Resurfacing project website at https://palihighway.org

 

5) NUUANU (WEEKEND/NIGHT WORK)

Lane closure on the Pali Highway (Route 61) in the Kailua-bound direction between the Pauoa Road underpass and Wylie Street overpass on Sunday night, June 2, through Friday morning, June 7, from 8:30 p.m. to 2:30 a.m., for the Pali Highway Resurfacing project. One lane will be tentatively closed from 2:30 a.m. to 5 a.m.

 

For more information, please visit the Pali Highway Resurfacing project website at https://palihighway.org

 

 

— KALAELOA BOULEVARD —

 

1) KAPOLEI (WEEKEND/NIGHT WORK)

Lane closure on Kalaeloa Boulevard in the northbound direction between Kapolei Parkway and Farrington Highway on Sunday night, June 2, through Wednesday morning, June 5, from 8 p.m. to 4:30 a.m., for the Kapolei Interchange Complex Phase 2 project.

 

For more information, visit the Kapolei Interchange Complex Phase 2 project website at https://www.buildkapolei.com/

 

 

— MIDDLE STREET —

 

1) KALIHI (SIDEWALK AND BIKE PATH CLOSURE)

The west shared use walkway and bike path are closed on Middle Street between North King Street and Kamehameha Highway on Friday night, May 31, through Friday night, June 7, over a 24-hour period, for the Middle Street pavement reconstruction project. Pedestrians are directed to use the east sidewalk.

 

 

 

For Immediate Release: May 30, 2019

19-0270

 

KAUAI LANE CLOSURES

FOR THE WEEKEND OF MAY 31 – JUNE 2

 

PLEASE NOTE:

Lane closure schedules may change at any time without further notice.
All projects are weather permitting.

 

— KAUMUALII HIGHWAY (ROUTE 50) —

 

1) HANAPEPE (24-HOUR CLOSURE)

The Hanapepe River Bridge on Kaumualii Highway (Route 50) between Puolo Road and Iona Road will be closed, and traffic will be shifted to the adjacent temporary bridge over a twenty-four-hour period, seven days a week. Speed limit is reduced to 25 mph.

 

 

— KUHIO HIGHWAY (ROUTES 56/560) —

 

1) KILAUEA (WEEKEND/NIGHT WORK)

Lane closure on Kuhio Highway (Route 56) in both directions between South Koolau Road and Kapuna Road on Sunday night, June 2, through Friday morning, June 7, from 8 p.m. to 5 a.m., for road improvements.

 

2) LIHUE (WEEKEND/NIGHT WORK)

Alternating two-lane closure on Kuhio Highway (Route 56) in both directions between North Leho Drive and Kapule Highway on Sunday night, June 2, through Friday morning, June 7, from 8 p.m. to 5 a.m., for road reconstruction and repaving.

 

3) WAIPA TO WAINIHA (EMERGENCY WORK, LOCAL ACCESS ONLY)

Limited local access to Kuhio Highway (Route 560) past Waipa Bridge is available for vehicles with county issued placards in both directions. Schedule for the weekend of Friday, May 31, through Sunday, June 2, is on the following schedule:

 

  • 5:30 a.m. – 8:20 a.m.
  • 12:45 p.m. – 2:15 p.m.
  • 5 p.m. – 11 p.m.

 

Sunday/Holiday access is between 6 a.m. to 11 p.m.

 

###

Patricia Wong

Information Specialist

Hawaii Department of Transportation

869 Punchbowl St. 96813

(808) 587-2160

[email protected]